Once the design is complete, we submit the net meter application and our design to Rocky Mountain Power for approval.

They check the design to make sure it doesn’t negatively affect the exhibiting electrical infrastructure in the immediate area.

This initial approval can take anywhere from 2-5 weeks. Due to the extensive time of review by RMP, we submit this application at the onset so the installation isn’t delayed.